Ultra Flexible
Ultra Flexible Healthcare Air Handling
Working directly with the NHS, private healthcare organisations and with construction & engineering contractors, our approach is always one of ultimate flexibility to guarantee both our modular and tailor-made units achieve:
- maximum energy efficiency
- legislative compliance incl. HTM 03-01
- minimum unit footprint
- required performance levels
The Project
With access to the 3rd floor plantroom restricted to a 700mm doorway and under pre-installed ductwork at a height of 1200mm, a flatpack solution with separated frame with individualised panels were required for the 9m x 2.1m air handling unit.
Built to achieve a minimum class L2 air leakage and incorporating run and standby supply and extract fans, the HTM 03-01 compliant unit now provides critical ventilation to a new operating theatre at the University Hospital North Tees.
Fully customised, the welded aluminium profile base was reduced from the standard 300mmm to 287m to connect seamlessly with pre-existing ductwork spigots and a quick release fan mechanism designed to ensure maximum uptime and unit reliability.
The Highlights
Ultimate Flat Pack Build: 700mm plantroom access required an extreme flatpack solution
HTM 03-01 2021 Compliant: Fully compliant with the latest HTM 03-01 legislation (2021).
Class L2 Air Leakage: On-site AHU casing build & testing to achieve class L2
Run & Standby EC Fans: Offering the ultimate in redundancy, efficiency and low noise levels